USAfixTM - Repair Guide (RG) - Master Email RG
- Check all hoses and fittings for leaks
 Level of Difficulty - MEDIUM  Estimated Completion Time - 30 minutes
TASKI - SWINGO 755B

Tools Required
Tool 
Wrench-Allen metric 6.0mm

Parts Required


Step Procedure & Parts & Tools
1 MAKE SURE THERE IS WATER IN TANK. PUSH MANUAL SOLUTION VALVE LEVER FORWARD TO OPEN POSITION (ECO MODELS ONLY!)

2 CHECK SOLUTION LINE AND DRAIN HOSE AT VALVE (LOCATED ON BACK LOWER LEFT CORNER) FOR LEAKS. MOVE SOLUTION LEVER TO OFF POSITION (ECO MODELS ONLY!)

3 LOCATE THE DRAIN HOSES ON BACK OF MACHINE

4 PULL THE BLUE CAPPED DRAIN HOSE FROM MACHINE TO INSPECT FOR LEAKS.

5 PULL THE RED CAPPED DRAIN HOSE FROM MACHINE TO INSPECT FOR LEAKS

6 PLACE HOSES NEAR DRAIN AND REMOVE THE CAPS TO DRAIN THE TANKS

7 LOCATE THE 2 TANK BOLTS AT THE FRONT BASE OF MACHINE. REMOVE THE 2 TANK BOLTS ON EACH SIDE OF BASE (SET BOLTS ASIDE)
Wrench-Allen metric 6.0mm

8 LIFT THE FRONT OF THE TANK TO OPEN THE MACHINE AND LOCATE THE BATTERIES

9 REMOVE THE BATTERIES FROM THE MACHINE AND LOWER TANK TO CLOSE MACHINE (NO NEED TO REINSTALL TANK BOLTS AT THIS TIME)

10 LAY THE MACHINE ON IT'S SIDE AND LOCATE ALL SOLUTION LINES UNDER MACHINE

11 VISUALLY INSPECT ALL THE SOLUTION HOSES AND FITTINGS FOR LEAKS. FEEL HOSES TO SEE IF WET.

12 STAND MACHINE UPRIGHT, REINSTALL BATTERIES, REINSTALL TANK BOLTS AND FILL TANK WITH WATER AND SOLUTION IF NEEDED
Wrench-Allen metric 6.0mm